I/O points and commissioning progress
Import the project's I/O points, move them from installed to commissioned as the site works, and see the progress by system and task.
2 min readLast updated
In this article
Every controlled or monitored point of a building system (a sensor, a valve, a fan command) is an I/O point. Each point moves forward: Designed, Installed, Wired, Tested, Commissioned. Its history keeps who moved it and when.
Import the points
Open the project and go to I/O points.
Select Import points and upload a CSV with the columns
point_tag,point_type,system,building,floor,zone,equipment_tag,description,device,task_code.Check the preview and import. A point whose tag already exists is updated, not added twice.
A project created from an award priced by the pricing system starts with its points already in the register (status Designed), from the points list of the awarded offer.
Update the site's progress
Filter the points (status, system, building, floor) or search by tag, and select them.
Select Update status and choose the new status. For Tested, give the result: Pass or Fail. A failed point stays Wired until it is tested again.
A point is Commissioned only after a passed test. Points already tested Pass move straight on; for points not tested yet, give the result Pass with the move. A batch with an untested or failed point is refused, and nothing moves.
Points only move forward; the steps you skip are stamped too. Open a point to see its history.
Progress
The tab shows how many points are at each status and the percentage commissioned. When your company turns on Progress from I/O points in Process settings, the progress of each task with points follows them: installed 25 %, wired 50 %, tested 75 %, commissioned 100 %.
Common questions
Why can the SAT not be recorded? When your company requires it, every point must be commissioned first. See Handover and acceptance.